Where to Use CROSSLOCK
Start from the structural member.
Slab, beam, column, footing, wall and other RCC work do not all use the same spacer. Start with where the spacer is required, then check the concrete cover and reinforcement condition.

Selection order
- Identify the RCC application.
- Check concrete cover or support level from the structural drawing.
- Confirm the reinforcement arrangement.
- Estimate products and quantities for that application.
01 · Application
Slab
A slab can need more than one reinforcement-positioning product. Bottom steel uses cover blocks, while top steel requires plastic rebar chairs. Beams and electrical conduits are calculated separately and then combined into the requirement.
- Bottom steel: select the cover block according to the cover specified on the structural drawing.
- Top steel: use a suitable plastic rebar chair; do not substitute a bottom cover block.
- Down beams and beam sides: assess separately using the beam arrangement.
- Electrical conduits: support at the intended level where required.
02 · Application
Beam
Beam bottom and beam sides are different conditions. Use the total beam length when available for a better quantity estimate.
- Down beam: select by the required cover and largest main-bar diameter.
- Beam sides: provide appropriate side-cover support for the cage.
03 · Application
Column
Column selection changes with column size and the specified concrete cover. The calculator also accounts for repeated shuttering stages over the floor height.
- Confirm the cover specified for each face.
- Check the reinforcement arrangement, column section and installation position.
04 · Application
Footing / Foundation
Foundation calculation changes with the type of foundation. The calculator therefore asks different dimensions for standalone footing, continuous footing, raft and pile foundation.
- Standalone footing: use mat dimensions and the number of footings.
- Continuous footing: use length and width or the appropriate project quantity.
- Raft foundation: assess mat area and any additional support zones.
- Pile foundation: determine cage length, number of piles and radial cover needs.
05 · Application
RCC Wall / Retaining Wall
Vertical reinforcement needs spacers on the wall faces before shuttering. Enter the wall area and choose the cover specified for the work.
- Select a vertical spacer compatible with the reinforcement and required wall cover.
06 · Application
Staircase
Waist slab, landings and step reinforcement can have different cover and support conditions. Follow the structural drawing and ask CROSSLOCK if the support condition is unclear.
- Follow the engineer’s detailed cover and reinforcement support requirements.
07 · Application
DPC / Plinth Beam
Select these narrow beam conditions from the required concrete cover and reinforcement arrangement. Ask CROSSLOCK if the detail differs from a normal beam.
- Treat narrow beam sections according to their specified concrete cover and bar arrangement.
08 · Application
Electrical Conduits
Where conduits need to be supported at an intended level inside the slab, the calculator provides a practical planning estimate from slab area.
- Select the conduit support from slab geometry and intended service level.
From application to product choice
The structural drawing and engineer’s project specification control the required cover, reinforcement position and support arrangement. CROSSLOCK’s selector helps with product and quantity planning.